Southampton

CEX

This project was the first CEX store completed by JMS. Given three weeks, we transformed an empty shell into a fully trading store. Initially, the project consisted of bringing the unit up to date with current fire regulations including fire boarding out the ceiling, substantial repairs were also necessary to the flooring before partition walls and first fix electrics could be installed. Once these works had been completed, we were able to carry out full interior decoration, alongside the installation of an entire new shop front and signage to fit CEX specifications. We installed a new ceiling grid and tiles, a new air conditioning system and new vinyl floor throughout the store. The final week on site saw the installation of the unitary supplied by CEX, the second fix electrical work was completed and the store was finished with a deep clean ready to hand back to the client.