Sheffield

Subway

The project was our first collaboration with the Subway group and their nominated suppliers. Completed over a 4 week duration starting with the striping out of existing fixtures and fittings completed in week 1 and then the first fix of utilities during week 2 along with the making good of walls, installation of new ceilings / flooring and installation of a bespoke raft above the customer serving area. Delivery of the bespoke unitary was received start of week 3 from H&K and installation was completed following a specification guide over a 5 day period. Week 4 saw the second fix of utilities, along with decoration to the refresh specification. The finished product was delivered on time with assistance of specialist contractors to commission the ovens and install the drinks unit.